Kaduna Refinery’ll begin production Dec. – NNPCL Boss, Kyari

The Group Managing Director of the Nigerian National Petroleum Company Limited (NNPCL), Mr. Mele Kyari, has disclosed that the refinery in Kaduna State would be ready for production by December 2024.

 

 

 

 

Mr. Kyari disclosed this during a meeting with the Independent Petroleum Marketers Association of Nigeria (IPMAN) and the Major Energy Marketers Association of Nigeria (MEMAN), in Abuja.

 

 

 

 

He disclosed that operations at the Port Harcourt refinery are scheduled to begin in two weeks.

 

READ ALSO: http://Nigeria’s Constitution, not people’s document – Tunji Abayomi

 

 

According to Kyari: “We did a mechanical completion of the (Port Harcourt) refinery, that was what we said in December. We now have crude oil already stocked in the refinery. We are doing regulatory compliance tests that must happen in every refinery before you start it, and I assure you that this Port Harcourt refinery will start in the next two weeks.

 

 

 

 

“Completing the mechanical work means that you are done with the rehabilitation work, now you have to test to see how it works. Of course, we have also completed the mechanical work on the Warri refinery.

 

 

 

 

 

“It is also undergoing regulatory compliance; processes that we are doing with our regulator, and this will soon be completed and it will be ready.

 

 

 

 

 

“The Kaduna refinery will be ready by December. We have not reached that stage in Kaduna, but we promise Kaduna will be delivered by December.”